Ranked by value of information
ActionResolvesCostDurationOwner
Re-quote element, both vendorsCOGS at 5K units$01 weekSean R.
Close Safety Requirements, book UL pre-reviewUL cleared by Dec 2026$4K3 weeksSean R.
Sketch B vs C decisionTwo-slot format$02 daysAllison K.
Price test at $165 with 40 waitlist buyersWould pay $120+, 68%$1.2K2 weeksPedram M.
Qualify Taiwan second sourceElement single source$8K6 weeksSean R.
Why this order

The element re-quote is first because it costs nothing, takes a week, and resolves the entry the entire margin rests on. It is also the cheapest possible disqualifier: if the re-quote lands above $62 the case changes shape before anyone spends on tooling.

The price test sits fourth rather than first despite addressing a load-bearing entry, because the 68% figure is already evidenced at low confidence and the test costs two weeks. Qualifying the second source is last: it is the most expensive action here, and the re-quote may make it unnecessary.

Decision branch points
Element re-quote landsUnder $62, plan as written. Over $62, the Taiwan qualification moves to first and the 5K run slips a quarter.week 1
UL pre-review outcomeClean, retail 2027 holds. A finding on cord tip-over costs six weeks and the foot redesign is already scoped for it.Jul 24
Campaign against comparable medianAt or above, the 2027 plan stands. At goal only, opex cuts to $450K and retail is skipped.post-launch
Stop conditions, agreed in advance

The campaign missing its goal is a stop, not a retry. Deposits are returned and the design is open-sourced. That was agreed while the outcome was still unknown, which is the only time a stop condition can honestly be set.

One more, not yet agreed and worth settling now: a re-quote above $70 leaves no version of this at $165, and the question becomes whether the product is a $189 machine rather than whether to continue.