| Action | Resolves | Cost | Duration | Owner |
|---|---|---|---|---|
| Re-quote element, both vendors | COGS at 5K units | $0 | 1 week | Sean R. |
| Close Safety Requirements, book UL pre-review | UL cleared by Dec 2026 | $4K | 3 weeks | Sean R. |
| Sketch B vs C decision | Two-slot format | $0 | 2 days | Allison K. |
| Price test at $165 with 40 waitlist buyers | Would pay $120+, 68% | $1.2K | 2 weeks | Pedram M. |
| Qualify Taiwan second source | Element single source | $8K | 6 weeks | Sean R. |
The element re-quote is first because it costs nothing, takes a week, and resolves the entry the entire margin rests on. It is also the cheapest possible disqualifier: if the re-quote lands above $62 the case changes shape before anyone spends on tooling.
The price test sits fourth rather than first despite addressing a load-bearing entry, because the 68% figure is already evidenced at low confidence and the test costs two weeks. Qualifying the second source is last: it is the most expensive action here, and the re-quote may make it unnecessary.
The campaign missing its goal is a stop, not a retry. Deposits are returned and the design is open-sourced. That was agreed while the outcome was still unknown, which is the only time a stop condition can honestly be set.
One more, not yet agreed and worth settling now: a re-quote above $70 leaves no version of this at $165, and the question becomes whether the product is a $189 machine rather than whether to continue.